To accommodate plant production days, the start of day can be changed from the Action Calendar default of midnight.
Select Tools on the Action Calendar's menu bar.
Select Setup.
The Setup dialog box displays.
Enter the following information in the Setup dialog box.
Day Start |
Enter a number from 01 to 12 |
AM/PM |
Choose AM or PM from the Menu field. |
Important: Day
Start cannot be changed when the project is running.
Changing the Day Start requires that the application be exited.