  1. Case Description

The existing project is running correctly.

Insure that it can be recovered from PCM.

  1. Recommended Procedure

The following procedure helps to insure that local and managed projects are properly managed and can be correctly recovered from the PCM Server.

Use this procedure consistently whenever making configuration changes to a managed CIMPLICITY project:

  1. Verify that all configuration applications are closed and remain closed throughout this process.

  2. Check in all checked out files

  3. Add project that will add in any missing files

  4. Check out project without get (to get all files that were modified without checking out)

  5. Check in project to update the managed project.

  6. Label Project

More information