Add a scheduled event. |
|
Modify a scheduled event. |
|
Delete a scheduled event. |
Add a Scheduled Event
If the event already exists:
Fill in the time for the event to occur.
Click the Browse button to the right of the Event field.
Select the appropriate event to schedule.
If the event does not exist:
Click the Popup menu button to the right of the Browse button.
Select New from the popup menu.
Guideline: Scheduling Time
Actions cannot be scheduled to at the exact same time as the start of the day. This is because this is the transition period from one day schedule to the next, and this time is ambiguous.
To help work with this limitation the start of day configuration has been modified so that the start of the day can be configured with 1 minute resolution.
The start of the day should be selected to coincide with a time between shifts that
Will have no need for scheduled activities
Is a natural breaking point from 1 day to the next.
Midnight is often a good time for this, but for others 3:00 am may be better.
Modify a Scheduled Event
Make sure the Action Calendar is in Day Type mode.
Double click on a scheduled event in an hour row of the Action Calendar Schedule part.
The Scheduled Event dialog box opens.
Do one of the following:
Change the time of the event.
Change the event.
Select Edit from the Event field popup menu to open the Event Properties dialog box.
Delete a Scheduled Event
Select the scheduled event in the hour Schedule part of the Action Dialog box.
Press the Delete key.